Project Img
Location:
Coal City, IL
Client:
Coal City USD #1
Architect:
Healy Bender & Associates

This new Early Childhood Development Center was the first phase of Coal City Unit School District #1’s expansion program. Sollitt was hired as Construction Manager at Risk with a Guaranteed Maximum Price early in the design process to provide cost and schedule analysis, value engineering and site logistics planning. The Sollitt team worked closely with the District and their architectural team during the pre-construction process. The project was delivered within budget with the highest level of quality.

  • Construction Manager at Risk with a Guaranteed Maximum Price
  • 83,173 square feet; 20 acres
  • Construction Duration - 12 months
  • Regular and Special Education Classrooms
  • Learning Resources Center
  • Computer, Music and Art labs
  • Multi-purpose Room, Kitchen and Gymnasium